Content
1.2 Construction Works Programme
1.4 License, Notification and Permits
1.5 Brief Summary of EM&A Requirements
2.2 Air Quality Monitoring
Parameter, Frequency and Duration
2.3 Monitoring Equipment and
Methodology and QA/ QC Procedure
3.2 Noise Monitoring
Parameter, Frequency and Duration
3.3 Monitoring Equipment,
Methodology and QA / QC Procedure
3.4 Maintenance and
Calibration
5. environmental site inspection and audit
6. environmental non-compliance
6.2 Summary of Environmental
Non-Compliance
6.3 Summary of Environmental Complaint
6.4 Summary of Environmental Summon
and Successful Prosecution
7.1 Construction Works and
Potential Environmental Issues in the next Reporting Period
8. ConclUsion, Comments and recommendation
8.2 Comments and Recommendations
List
of Tables
Table I Summary of EM&A Activities in the Reporting
Period
Table II Summary of Exceedance in the Reporting Period
Table 1.1 Status of Environmental License, Notification and
Permits
Table 1.2 Summary of Status of Submission under EP-602/2021
Table 2.1 Air Quality Monitoring Stations for Construction Phase
Table 2.2 Impact Air Quality Monitoring Parameter, Duration and Frequency
Table 2.3 Impact Air Quality Monitoring Equipment
Table 2.4 Action and Limit Levels for 1-hour TSP
Table 2.5 Summary of Impact 1-hour TSP Monitoring Results
Table 2.6 Influencing Factors at / near Air Quality Monitoring
Stations
Table 3.1 Noise Monitoring Stations during Construction Phase
Table 3.2 Construction Noise Monitoring Parameter, Frequency and
Duration
Table 3.3 Construction Noise Monitoring Equipment
Table 3.4 Action and Limit Levels for Construction Noise
Monitoring
Table 3.5 Summary of Construction Noise Monitoring Results
Table 3.6 Influencing Factors at Noise Monitoring Stations
Table 4.1 Summary of Waste Generated in the Reporting Period
Table
5.1 Summary of Site
Inspections Observation and Recommendations
List
of Figure
Figure 1.1 Project
Layout Plan
Figure 2.1 Air
Quality Monitoring Stations
Figure 3.1 Construction
Noise Monitoring Stations
List of Appendices
Appendix A Master
Construction Programme for the Project
Appendix B Project
Organization Chart and Key Personnel Contact
Appendix C Event
and Action Plans
Appendix D Project
Implementation Schedule
Appendix E Air
Quality and Noise Monitoring Equipment Calibration Certification
Appendix F Environmental
Monitoring Schedule
Appendix G Air
Quality Monitoring Results and Graphical Presentation
Appendix H Extract
of Meteorological Observations for Hong Kong (Kai Tak)
Appendix I Noise
Monitoring Results and Graphical Presentation
Appendix J Waste
Generation in the Reporting Month
Appendix K Summary
of Complaint, Notification of Summons and Prosecution and Cumulative Complaint
Log
This is the second Monthly
Environment Monitoring and Audit (EM&A) Report for Relocation of Diamon
Hill Fresh Water and Salt Water Service Reservoirs to Caverns (the Project).
This report was prepared by Acuity Sustainability Consulting Limited under
Contract No. 21/WSD/21 (hereafter called “the Contract”). This report documents the findings of EM&A
works during the reporting period from 1 May to 31 May 2023.
Key Construction Works in the
Reporting Period
A summary of construction
activities undertaken during the reporting period is presented below:
·
Tree felling and site clearance
at Portion 3;
·
Demolition of existing shed at
Portion 4;
·
Relocation of transit nursery and
other LCSD’s facilities to Portion 4;
·
Underground utilities survey; and
·
Hoarding erection and site setup.
Environmental Monitoring and Audit
Programme
The monthly EM&A programme
was undertaken by the Environmental Team in accordance with the EM&A
Manual. A summary of the monitoring and audit activities during the reporting
period is presented below:
Table I Summary
of EM&A Activities in the Reporting Period
EM&A Activities |
Date |
1-hour TSP Monitoring |
5, 10, 16, 22 and 27 May 2023 |
Construction Noise Monitoring |
5, 10, 16 and 22 May 2023 |
Weekly Environmental Site Inspection |
5, 12, 17 and 25 May 2023 |
Breaches of Action and Limit
Levels
A summary of the environmental monitoring
exceedance of the reporting period is tabulated in Table II.
Table II Summary
of Exceedance in the Reporting Period
Environmental Monitoring |
Parameter |
No. of non-project related
exceedances |
Total no. of non-project
related exceedances |
No. of exceedances related to the project |
Total no. of exceedances
related to the project |
||
AL |
LL |
AL |
LL |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
0 |
0 |
0 |
Noise |
Leq(30-min) |
0 |
0 |
0 |
0 |
0 |
0 |
Air Quality
No action or limit levels
exceedance was recorded for 1-hour TSP monitoring during the reporting period.
Construction Noise
No action or limit levels
exceedance was recorded for construction noise monitoring during the reporting
period.
Complaint Log
No environmental complaint was
received in the reporting period.
Notification of Summons and
Successful Prosecutions
No notification of summons or
successful prosecutions was received in the reporting period.
Reporting Change
There was no reporting change in
the reporting period.
Future Key Issues
Key issues to be considered in
the next three months included:
·
Boulder survey;
·
Open trench for mainlaying and Mainlaying;
·
Pipe Jacking of trenchless;
·
Hoarding erection and site setup;
·
Tree transplant and site
clearance;
·
Trial pit excavation;
·
Formation of piling platform at
Zone 1 and Zone 2;
·
Pipe piling for tunnel ELS wall;
·
Relocation of transit nursery and
other LCSD’s facilities to Portion 4;
·
Civil construction works, e.g.
water supply;
·
Trial pit excavation; and
·
Pre-construction condition survey.
Potential environmental impacts
arising from the above construction activities are mainly associated with
construction dust, construction noise, water pollution control, waste
management and landscape and visual.
1.1.1
The relocated Diamond Hill Fresh Water and Salt
Water Service Reservoirs (DHSRs) will be constructed in a series of caverns
linked by access tunnels and adits. The relocated
Diamond Hill Fresh Water Service Reservoirs (DHFWSR) and Diamond Hill Salt
Water Service Reservoirs (DHSWSR) will be compartmented while the existing Diamond
Hill Pumping Station (DHPS) will be split into two (2) pump houses for fresh
and salt water supply when relocated.
1.1.2
Ancillary facilities to be constructed near the
tunnel portal may include transformer room, switch room, emergency generator
room, control room, ventilation building, and pumping station control room,
which will be constructed in an above-ground building outside the tunnel.
1.1.3
The scope of the Project comprises the following:
a)
Construction of the relocated DHSRs and associated
pumping stations and water main laying works;
b)
Construction of tunnels, adits,
ventilation system and caverns for accommodating the relocated DHSRs and the
associated facilities;
c)
Terminating the operation of the existing DHSRs and
the associated facilities; and
d)
All other associated works that are incidental to
and necessary for the completion of the Project.
1.1.4
The major construction activities of the Project
include earthworks, drilling and blasting, construction of concrete structures,
handling and transportation of excavated materials, water mains laying,
installation of electrical and mechanical (E&M) equipment and material
transportation. The operation of the
existing DHSRs and the associated facilities will be terminated after the
completion of the testing and commissioning of the relocated DHSRs. Under the Project, the existing DHSRs and
associated facilities will be retained after termination of the operation. The subsequent demolition works will be
carried out by other government departments/ project proponents.
1.1.5
The Project construction was commenced on 31 March
2023 and the completion date for the construction works would be on 12 April
2027.
1.1.6
The Project is a Designated Project under Item Q.2,
Part I of Schedule 2 of the Environmental Impact Assessment Ordinance,
"Underground Rock Caverns", which requires an environmental permit
from Environmental Protection Department for its construction and operation.
1.1.7
Pursuant to the Environmental Impact Assessment
Ordinance (EIAO), the Director of Environmental Protection Department (EPD)
granted the Environmental Permits (EP-602/2021) to the Water Supplies
Department (WSD) for the Project.
1.1.8
Acuity Sustainability Consulting Limited (ASCL) is
commissioned by Chun Wo – Sinohydro Joint Venture to
undertake the role of Environmental Team under the Environmental Permit (EP)
EP-602/2021, and to carry out the EM&A programme in fulfilment of the
EM&A Manual, and other requirements stipulated in the associated EIA
Report.
1.1.9
This is the second Monthly EM&A Report
summarizing the key findings of the construction phase EM&A programme from 1
May to 31 May 2023 (the reporting period) and is submitted to fulfil the
requirements in Conditions 3.4 of EP-602/2021 and section 13.3 of the EM&A
Manual of the Project.
1.2.1
The construction works of the Project was commenced
on 31 March 2023. The construction works
programme, and the location of construction works of the Project are shown in Appendix
A and Figure 1.1,
respectively. A summary of construction activities undertaken during the
reporting period is presented below:
·
Tree felling and site clearance
at Portion 3;
·
Demolition of existing shed at
Portion 4;
·
Relocation of transit nursery and
other LCSD’s facilities to Portion 4;
·
Underground utilities survey; and
·
Hoarding erection and site setup.
1.3.1
Different parties with different levels of
involvement in the Project organization include:
·
Project Proponent: Water Supplies Department (WSD)
·
Supervisor/Engineer’s Representative (ER): Binnies
Hong Kong Limited
·
Contractor: Chun Wo - Sinohydro
Joint Venture
·
Environmental Team (ET): Acuity Sustainability
Consulting Limited
·
Independent Environmental Checker (IEC): Umwelt
Consulting Limited
1.3.2
The key personnel contact names and telephone number
are presented in Appendix B.
1.4.1
A summary of the relevant permit, licences, and/ or
notifications on environmental protection for this Project are presented in Table
1.1.
Table 1.1 Status of Environmental License,
Notifications and Permits
Permit / License No. |
Valid Period |
Status |
|
From |
Expired On |
||
Environmental Permit |
|||
EP-602/2021 |
14/12/2021 |
- |
Valid |
Notification Pursuant to Section 3(1) of the Air
Pollution Control (Construction Dust) Regulation |
|||
Ref. No.: 487301 |
09/12/2022 |
- |
Valid |
Billing
Account for Disposal of Construction Waste |
|||
7046085 |
04/01/2023 |
- |
Valid |
Registration
of Chemical Waste Producer |
|||
WPN 5213-282-C4760-0 |
30/12/2022 |
- |
Valid |
Effluent
Discharge License under Water Pollution Control Ordinance |
|||
WT00043965-2023 |
31/05/2023 |
31/05/2028 |
Valid |
1.4.2
The submission status of the EP and the
implementation status of the mitigation measures stated in the EP had been
reviewed, all submission were submitted/ deposited to the Director of
Environmental Protection (DEP) on schedule, no non-compliance of EP conditions
was recorded during the reporting period. The summary of submission status
under Environmental Permit EP-602/2021 are summarized in Table
1.2.
Table
1.2 Summary of Status of Submission under
EP-602/2021
EP Condition |
Title of Submission |
Submission Status |
1.11 |
Commencement Date of Construction |
Notified the DEP on 22 Feb 2023 |
2.9 |
Management Organization(s) |
Informed the DEP on 20 Feb 2023 |
2.10 |
Environmental Permit (EP) Submission Schedule |
22 Feb 2022 (1st Submission) |
2.11 |
Construction Works Schedule and Location Plan |
28 Feb 2023 (Deposited) |
2.12 |
Construction Noise Management Plan (CNMP) |
28 Feb 2023 (Deposited) (Comments were issued by the EPD
on 8 Mar 2023 and the CNMP is being revised.) |
2.13 |
Waste Management Plan (WMP) |
28 Feb 2023 (Deposited) (Comments were issued by the EPD
on 3 Apr 2023 and the WMP is being revised.) |
2.14 |
Landscape and Visual Mitigation Plan (LVMP) |
28 Feb 2022 (1st Submission) (Comment were issued by the EPD
on 29 Mar 2023 and the LVMP is being revised.) |
3.3 |
Baseline Monitoring Report |
17 Mar 2023 (1st Submission) 27 Apr 2023 (2nd Submission) |
3.4 |
Monthly EM&A Report (Apr 2023) |
15 May 2023 |
4.2 |
Dedicated Internet Website |
2 May 2023 |
1.4.3
Following the EPD’s comments on the Baseline Monitoring
Report (Ref. No. BMR-3.1, dated 17 March 2023), updating of air quality and
noise monitoring locations were proposed, including cancellation of noise
monitoring station at Tower 1, Meridian Hill (NM-1), resumption of air quality
and noise monitoring stations at Block 6, Tsui Chuk Garden (i.e. DM-4 and NM-4)
and proposal of new noise monitoring locations at Wo Tin
House, Shatin Pass Estate (NM-5) and Sheung Fung Street Customs Staff
Quarter (NM-6).
1.4.4
Additional baseline monitoring for air quality
monitoring station DM-4, and noise monitoring stations NM-4, NM-5 and NM-6 was
carried out between 2 May and 16 May 2023. The Baseline Monitoring Report was
updated with all baseline monitoring results included, certified by the ET
Leader, and verified by the IEC on 30 May 2023. Submission of the Baseline
Monitoring Report is scheduled on 1 June 2023.
Air Quality
1.5.1
In accordance with the EM&A Manual, the ET shall carry out impact monitoring during construction phase of the project. For 1-hour Total Suspended
Particulates (TSP) monitoring, the sampling frequency of at least three times
every six days should be undertaken when the highest dust impact occurs.
1.5.2
Action and Limit Levels for the 1-hour TSP monitoring works are discussed
in Section
2.4. Should non-compliance of the criteria occur,
action in accordance with the Event and Action Plan presented in Appendix C shall be carried out.
1.5.3
The air quality mitigation measures detailed in the EM&A
Manual were recommended to be implemented during the construction phase. The implementation statuses of these measures
are presented in Appendix D.
Noise Monitoring
1.5.4
Construction noise monitoring should be carried out at the designated
monitoring stations directly affected by the construction works once every week
after the commencement of construction. During construction works, one set of Leq(30-min) measurement at each
station between 0700 and 1900 hours on normal weekdays shall be taken. If
construction works are extended to include works during the period between 1900
and 0700 hours, additional weekly impact monitoring shall be carried out during
evening and night-time works.
1.5.5
Action and Limit Levels for the noise monitoring are discussed in Section 3.5. Should non-compliance of the
criteria occur, action in accordance with the Event and Action Plan presented
in Appendix
C shall be
carried out.
1.5.6
The noise mitigation measures detailed in the EM&A Manual
are recommended to be implemented during the construction phase. The implementation statuses of these measures
are presented in Appendix D.
Environmental Requirements in Contract Documents
1.5.7
According to Particular Specification (PS), the Contractor
shall undertake environmental protection measures to reduce the environmental
impacts arising from the execution of the works. The Contractor shall also observe and comply
with relevant environmental protection and pollution control ordinances. The Contractor shall design, construct,
operate and maintain pollution control measures to ensure compliance with the
contract provisions as well as the environmental ordinances and their
regulations.
1.5.8
The Contractor shall also:
· Implement air pollution and noise
abatement practices as specified in PS;
· Minimise generation of wastewater
from the Site;
· On-site sorting of Construction and
Demolition (C&D) Materials;
·
Establish a mechanism to record the quantities of C&D materials
generated each month, using the monthly summary “Waste Flow Table”;
·
Control the use of timbers;
·
Implement a trip ticket system (TTS) for tracking the removal of C&D
materials from the Site to the disposal grounds;
·
Prepare an Environmental Management Plan (EMP) in accordance with GS
Section 25 and PS for implementation on the Site to reduce environmental
nuisance and C&D materials arising from Works, throughout the construction
period;
·
Arrange weekly environmental walk to inspect the Site, checking that the
environmental performance of the Site is satisfactory and in compliance with
the requirements under the contract and EMP; and
·
Carry out site specific induction training about environmental management
as well as safety for all staffs and workers, and provide toolbox talks for
workers on environmental nuisance abatement and waste management.
2.1.1
The air quality monitoring locations for impact monitoring during the
reporting period are listed in Table 2.1 and presented in Figure 2.1.
Table 2.1 Air Quality Monitoring Stations for
Construction Phase
ID |
Description |
Coordinates |
|
Northing |
Easting |
||
DM-1 |
Tennis
Court near Tin Ma Court |
822705 |
837047 |
DM-2 |
Chun
Sing House, Tin Ma Court |
822673 |
837143 |
DM-3 |
Grace
Methodist Church Kindergarten |
822782 |
837227 |
DM-4 (1) |
Block
6, Tsui Chuk Garden |
822926 |
837246 |
DM-4a (2) |
Road pavement near Wang King House, Tin Wang Court |
822854 |
837340 |
Notes:
1.
Following the EPD’s
comment on the Baseline Monitoring Report (Ref. No. BRM-3.1, dated 17 March
2023), air quality monitoring at DM-4 was resumed. Baseline monitoring for air quality monitoring
station DM-4 was then carried out between 2 May and 16 May 2023. Impact monitoring at DM-4 was commenced on 22
May 2023.
2.
An additional air quality
monitoring station DM-4a was proposed by the ET and agreed by the ER, IEC and
EPD.
2.2.1
Table 2.2 summarized
the monitoring parameter, duration, and frequency of impact air quality
monitoring.
Table 2.2 Impact
Air Quality Monitoring Parameter, Duration and Frequency
Parameter |
Frequency |
Duration |
1-hour TSP |
3 times every 6 days |
Throughout the construction phase |
Proposal of Using Portable Direct Reading Dust Meter
2.3.1
Direct reading dust meters were used for measuring 1-hour TSP levels
during the impact air quality monitoring. According to Section 4.4.1 of the EM&A
Manual, the proposed use of direct reading dust meters was submitted to and
agreed by the IEC.
2.3.2
Sufficient number of monitoring instruments were prepared by the ET for
carrying out the impact monitoring. All
equipment and associated instrumentation were clearly labelled.
2.3.3
Wind data were collected from
the records of Hong Kong Observatory Kai Tak Wind Station (22.30966N,
114.21336E), which is located at the
south-eastern side of runway of the former Kai Tak Airport about 4.5 km
south-east from the project site.
2.3.4
Equipment used in the impact air quality monitoring programme is
summarised in Table 2.3. Calibration
certificates for the impact air quality monitoring equipment are attached in Appendix E.
Table 2.3 Impact Air Quality
Monitoring Equipment
Equipment |
Brand and Model |
Serial No. |
Calibration Due Date |
Direct Reading Dust Meter |
Sibata LD-5R |
851820 |
15/10/2023 |
882109 |
15/10/2023 |
||
PC-3A(E) |
JC-220710221 |
08/10/2023 |
Maintenance and Calibration
2.3.5
Direct reading dust meters have been calibrated against high volume
samplers (HVSs) annually. A 2-day, three
3-hour measurement results per day from direct reading dust meters were taken
to compare with the sampling results from the HVSs. The correlation between the direct reading
dust meters and the HVSs were then concluded.
By accounting for the correlation factor, the direct reading dust meters
are considered to achieve comparable results as that of the HVSs.
2.3.6
The 1-hour TSP measurement follows the instruction provided in the
manufacturer's manual. Before initiating
a measurement, zeroing the portable dust meter was carried out to ensure the
accuracy of each measurement.
2.4.1
The action and limit levels were established in accordance with the
EM&A Manual. Table 2.4 presents the action and limits levels for 1-hour TSP monitoring. Should non-compliance of the criteria occur,
action in accordance with the Event and Action Plan presented in Appendix C shall be carried out.
Table 2.4 Action
and Limit Levels for 1-hour TSP
Monitoring
Station |
Action
Level (µg/m3) |
Limit Level (µg/m3) |
DM-1 |
300.1 |
500 |
DM-2 |
289.0 |
|
DM-3 |
289.7 |
|
DM-4 |
294.9 |
|
DM-4a |
291.6 |
2.5.1
The impact air quality monitoring was conducted on 5, 10, 16, 22 and 27
May 2023. The impact air quality
monitoring schedule for the reporting period is shown in Appendix F.
2.5.2
The monitoring results and graphical presentation of impact air quality
monitoring are shown in Appendix G. No action
or limit levels exceedance was recorded in the reporting period.
Table 2.5 Summary of Impact 1-hour TSP Monitoring
Results
Monitoring
Station |
TSP
Concentration, μg/m3 |
Action Level |
Limit Level |
||
Average |
Minimum |
Maximum |
|||
DM-1 |
90 |
75 |
97 |
300.1 |
500 |
DM-2 |
78 |
64 |
91 |
289.0 |
|
DM-3 |
66 |
58 |
73 |
289.7 |
|
DM-4 (1) |
66 |
57 |
72 |
294.9 |
|
DM-4a |
70 |
61 |
80 |
291.6 |
Remark: (1) Impact
air quality monitoring at DM-4 was commenced on 22 May 2023.
2.5.3
During the impact air quality monitoring, the major dust sources at each
monitoring stations were summarized in Table 2.6.
Table 2.6 Influencing
Factors at / near Air Quality Monitoring Stations
Monitoring
Stations |
Influencing
Factors |
DM-1 |
Not identified |
DM-2 |
Not identified |
DM-3 |
Not identified |
DM-4 |
Not identified |
DM-4a |
Not identified |
2.5.4
Weather conditions during impact monitoring are presented in Appendix G and extracts of wind data recorded
at Kai Tak Wind Station available from the Hong Kong Observatory are presented
in Appendix
H.
3.1.1
The monitoring locations for construction noise monitoring
are listed in Table 3.1 and shown
in Figure 3.1.
Table 3.1 Noise
Monitoring Stations during Construction Phase
ID |
Description |
Measurement |
Coordinates |
|
Northing |
Easting |
|||
NM-2 |
Chun
Sing House, Tin Ma Court |
Façade |
822668 |
837143 |
NM-3 |
Grace
Methodist Church Kindergarten |
Façade |
822782 |
837227 |
NM-4 (2) |
Block
6, Tsui Chuk Garden |
Façade |
822926 |
837246 |
NM-4a (1) |
Road pavement near Wang King House, Tin Wang Court |
Free field |
822854 |
837340 |
NM-5 |
Wo Tin House,
Shatin Pass Estate |
Façade |
823360 |
838143 |
NM-6 |
Sheung Fung
Street Customs Staff Quarters |
Free field |
823134 |
838412 |
Notes:
The
noise monitoring station proposed in the EM&A Manual (NM-1) was not
available for baseline and impact monitoring. Therefore, impact monitoring at NM-1 was cancelled
and agreed by the ER, IEC and EPD.
(1) An additional noise monitoring station NM-4a
was proposed by the ET and . agreed by the ER, IEC and EPD.
(2) Following the EPD’s comment on the Baseline
Monitoring Report (Ref. No. BRM-3.1, dated 17 March 2023), noise monitoring
station was resumed at NM-4. Baseline
monitoring for noise monitoring station NM-4 was then carried out between 2 May
and 16 May 2023. Impact monitoring at
NM-4 was commenced on 22 May 2023.
3.1.2
No construction work was conducted within 300m
radius of noise monitoring station NM-5 and NM-6. Thus, no construction noise
monitoring was carried out at these two noise monitoring stations in the
reporting period.
3.2.1
Construction noise level was measured by the ET and measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq(30-min)
was adopted as the monitoring parameter for the construction noise
monitoring.
3.2.2
As supplementary information for data auditing, statistical results such
as L10 and L90 were also obtained for
reference.
3.2.3
Table 3.2 summarized the monitoring
parameters, duration, and frequency of construction noise monitoring.
Table
3.2 Construction Noise Monitoring
Parameter, Frequency and Duration
Parameters |
Time |
Frequency |
Duration |
Leq(30-min) |
0700 and 1900 hours on normal weekdays |
once every week |
Throughout the construction phase |
3.3.1
As referred to the technical memorandum (TM) issued under the NCO, sound
level meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications were used
for carrying out the construction noise monitoring.
3.3.2
Noise measurements were not made in fog, rain, wind with a steady speed
exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed was checked with a portable
wind speed meter capable of measuring the wind speed in m/s.
3.3.3
Sufficient numbers of noise measuring equipment and associated
instrumentation were prepared by the Environmental Team. All the equipment and associated
instrumentation were clearly labelled.
3.3.4
Wind data were collected from
the records of Hong Kong Observatory Kai Tak Wind Station (22.30966N,
114.21336E), which is located at the
south-eastern side of runway of the former Kai Tak Airport about 4.5 km
south-east from the project site.
3.3.5
The monitoring procedures are as follows:
·
For façade measurement, the monitoring station was set at a point 1 m
from the exterior of the sensitive receivers building façade and set at a
position 1.2 m above the ground. For
free-field measurement, the monitoring station was set at a position 1.2 m above the ground.
·
The battery condition was checked to ensure good functioning
of the meter.
·
Parameters such as frequency weighting, the time weighting
and the interval were set as follows:
·
Frequency weighting: A
·
Time weighting : Fast
·
Interval :
30 minutes (Leq(30-min))
would be determined for daytime noise by calculating the logarithmic average of six Leq(5-min) data
·
Prior to and after each noise measurement, the meter was calibrated using
an acoustic calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level
before and after measurement is more than 1.0 dB, the measurement was
considered invalid and repeat of noise measurement will be required after
re-calibration or repair of the equipment.
·
At the end of the monitoring period, the values of Leq,
L90 and L10 were recorded. In addition, noise sources were recorded on a
standard record sheet.
3.3.6
Table 3.3 summarized the noise monitoring equipment used during the construction
noise monitoring. Calibration
certificates for the impact noise monitoring equipment are attached in Appendix E.
Table 3.3 Construction Noise
Monitoring Equipment
Equipment |
Model (Serial Number) |
Calibration Due Date |
Sound Level Meter |
Nti-XL2 (A2A-13548-E0) |
05/02/2024 |
Sound Calibrator |
Rion NC 75 (35124529) |
08/11/2023 |
3.4.1
Maintenance and calibration procedures are as follows:
· The microphone head of the sound
level meter and calibrator were regularly cleaned with a soft cloth; and
· The sound level meter and acoustic
calibrator were calibrated annually by a HOKLAS accredited laboratory or the
manufacturer.
3.5.1
The Action and Limit levels were established in accordance with the
EM&A Manual. Table 3.4 presents the Action and Limit Levels for construction noise. Should
non-compliance of the criteria occur, action in accordance with the Event and
Action Plan presented in Appendix C shall be carried out.
Table 3.4 Action and Limit Levels for Construction
Noise Monitoring
Monitoring
Stations |
Action Level |
Limit Level |
Time Period |
NM-2 |
When
one documented complaint is received |
75
dB(A) |
0700
- 1900 hours on normal weekdays |
NM-3 |
70/
65 dB(A) * |
||
NM-4 |
75
dB(A) |
||
NM-4a |
75
dB(A) |
||
NM-5 |
75
dB(A) |
||
NM-6 |
75
dB(A) |
Notes:
If
works are to be carried out during restricted hours, the conditions stipulated
in the construction noise permit issued by the Noise Control Authority have to
be followed.
* Reduce to 70 dB(A) for schools and 65 dB(A)
during school examination periods.
3.6.1
The construction noise monitoring was conducted on 5, 10, 16 and 22 May
2023. The monitoring schedule is presented in Appendix F.
3.6.2
The construction noise monitoring results are summarized in Table 3.5. No Action or Limit levels exceedance was
recorded in the reporting period. Details
of the results and graphical presentation are shown in Appendix I.
Table 3.5 Summary
of Construction Noise Monitoring Results
Monitoring Station (1) |
Noise Level, dB(A) |
Limit Level |
||
Leq(30-min) |
||||
Mean |
Minimum |
Maximum |
||
NM-2 |
70.6 |
69.9 |
71.8 |
75 dB(A) |
NM-3 |
65.3 |
64.8 |
66.2 |
70/ 65 dB(A) (2) |
NM-4 (3) |
65.1 |
65.1 |
65.1 |
75 dB(A) |
NM-4a |
72.5 |
71.9 |
73.0 |
75 dB(A) |
Note:
(1)
Construction
noise monitoring at NM-4 and NM-5 will commence when construction works are
undertaking near these stations.
(2)
Reduce
to 70 dB(A) for schools and 65 dB(A) during school examination periods.
(3)
Impact
monitoring at NM-4 was commenced on 22 May 2023.
3.6.3
Weather conditions during impact monitoring are presented in Appendix I and extracts of wind data recorded
at Kai Tak Wind Station available from the Hong Kong Observatory are presented
in Appendix
H.
3.6.4
During the construction noise monitoring period, the influencing factors
which may affect the results are summarized in Table 3.6.
Table 3.6 Influencing Factors at Noise Monitoring
Stations
Monitoring
Stations |
Influencing
Factors |
NM-2 |
Road traffic noise, construction noise
from 76 Broadcast Drive project |
NM-3 |
Road Traffic Noise |
NM-4 |
Road Traffic Noise |
NM-4a |
Road Traffic Noise |
4.1.1
Waste generated from the Project includes inert construction and
demolition (C&D) materials and non-inert C&D wastes in the reporting
period. The amount of waste generated by the construction works of the Project
during the reporting period is shown in Table 4.1 and the cumulative waste flow
table was presented in Appendix J.
Table 4.1 Summary of Waste Generated in the Reporting Period
Month |
Actual Quantalities of Inert
C&D Materials Generated Monthly |
Actual Quantities of C&D Wastes
Generated Monthly |
Actual Quantities of C&D Wastes
Recycled |
|||||||||||||
Total Quantity Generated |
Broken Concrete (Including rock for recycling into
aggregates) |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
Metals |
Paper / Carboard Packing |
Plastics |
Chemical Waste |
Others e.g., general refuse |
Metals |
Paper/ cardboard packaging |
Plastics (bottles/ containers, plastic
sheets/foam package material) |
Yard Waste |
Others |
|
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000m3) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000m3) |
|
May 2023 |
0.90365 |
0.00000 |
0.00000 |
0.00000 |
0.90365 |
0.00000 |
0.00000 |
0.00000 |
0.00000 |
0.00000 |
0.02411 |
0.00000 |
0.00000 |
0.00000 |
0.00000 |
0.00000 |
4.1.2
Construction and demolition (C&D) materials sorting was carried out
on site. Sufficient receptacles were
provided for general refuse collection and sorting. Excavated inert C&D materials were reused
to minimize the disposal of C&D waste to public fill.
4.1.3
The Contractor was advised to minimize the amount of waste through
recycling or reusing. All applicable
mitigation measures stipulated in the EM&A Manual and waste management
plans shall be fully implemented.
5.1.1
Site inspections were carried out by the ET on a weekly basis
to monitor the implementation of proper environmental pollution control
mitigation measures for the Project. During
the reporting period, site inspections were carried out 5, 12, 17 and 25 May
2023. Joint site inspection with the ER,
the Contractor and the IEC was carried out on 17 May 2023.
5.1.2
During the site inspections in the reporting period, no
non-conformance was identified. Key
observations and reminders during the site inspections are described in Table
5.1.
Table
5.1 Summary of Site Inspection Observations
and Recommendations
Inspection Date |
Key Observation / Reminders |
Follow-up Action |
5 May 2023 |
No major environmental deficiency was
observed. |
N/A |
12
May 2023 |
No major environmental deficiency was
observed. |
N/A |
17
May 2023 |
1. At Portion 3, the Contractor was reminded
to cover the temporary stockpile on site by impervious tarpaulin sheets before
backfilling. (Reminder) |
1. The temporary stockpile on site was
covered by impervious tarpaulin sheets. |
25
May 2023 |
1. At Portion 3, the Contractor shall water
the dusty material during excavation in the site area. (Reminder) |
1. Water spraying during the excavation was
implemented. |
5.1.3
According to the EIA Report, EP and the EM&A Manual, the
mitigation measures detailed in the documents are recommended to be implemented
during the construction phase. A summary
of the Project Implementation Schedule is provided in Appendix D.
6.1.1
No Action Level or Limit Level exceedance was recorded for 1-hour TSP
monitoring in the reporting period.
6.1.2
No Action Level or Limit Level exceedance was recorded for construction
noise monitoring in the reporting period.
6.1.3
Should the monitoring results of the environmental monitoring
parameters at any designated monitoring stations indicate that the Action/
Limit Levels are exceeded, the actions in accordance with the Event and Action
Plans in Appendix C would be carried out.
6.2.1
No environmental non-compliance was recorded in the reporting period.
6.3.1
No environmental complaint was received in the reporting period. The Cumulative Complaint Log is presented in Appendix K.
6.4.1
There was no successful environmental prosecution or notification of
summons received since the Project commencement. The Cumulative Log for environmental summon
and successful prosecution is presented in Appendix K.
7.1.1
The construction programme for the Project for the next
reporting period is presented in Appendix A.
7.1.2
Works to be undertaken in the next three months are
summarized below:
·
Boulder survey;
·
Open trench for mainlaying and Mainlaying;
·
Pipe Jacking of trenchless;
·
Hoarding erection and site setup;
·
Tree transplant and site clearance;
·
Trial pit excavation;
·
Formation of piling platform at Zone 1 and Zone 2;
·
Pipe piling for tunnel ELS wall;
·
Relocation of transit nursery and other LCSD’s facilities to Portion 4;
·
Civil construction works, e.g. water supply;
·
Trial pit excavation; and
·
Pre-construction condition survey.
7.1.3
Potential environmental impacts arising from the above
construction activities are mainly associated with construction dust impact,
noise impact, water quality impact, waste management and landscape and visual.
7.2.1
The key environmental mitigation measures for the Project in
the coming reporting period associated with above construction activities will
include:
Dust
·
Regular watering to
reduce dust emissions from exposed site surface;
·
Stockpile of dusty
materials shall be covered entirely by impervious sheeting;
·
Provide vehicles washing
facilities at all site exits to wash away any dusty materials from vehicle
body;
·
NRMM Labels should be
displayed on the applicable equipment on site by the Contractor;
·
All vehicle and plant should
be cleaned before they leave a construction site.
Noise
·
Only well-maintained
plant should be operated on-site, and plant should be maintained regularly
during the construction programme;
·
Quality Powered
Mechanical Equipment (QPME) should be adopted as far as possible.
Water
Quality
·
No effluent discharge
would be allowed before the effluent discharge license is acquired.
·
Surface run-off from
construction sites should be discharged into dedicated discharge point via
adequately designed sand/ silt removal facilities;
·
Channels/ earth bunds/
sandbags barriers should be provided on site to properly direct stormwater to
silt removal facilities;
·
Silt removal facilities,
channels and manholes should be maintained, and the deposited silt and grit
should be removed regularly;
·
Open stockpiles of
construction materials on sites should be covered with tarpaulin or similar
fabric during rainstorms;
·
Perimeter channels should
be provided on site boundaries where necessary to intercept stormwater run-off
from outside the site so that it will not wash across the site.
Waste
Management
·
Provision of sufficient
waste disposal points and regular collection of waste;
·
Regular cleaning and
maintenance programme for drainage system;
·
Chemical containers shall
be stored with drip tray underneath.
Ecology
·
Minimize loss of habitats
and associated wildlife;
·
Using directional
lighting to prevent excessive light spill into adjacent natural habitat and
disturbance to nocturnal fauna.
Landscape
and Visual
·
Construction activities
shall be carefully designed to minimize impact on existing retained trees;
·
Adequate tree protection
measures shall be provided for the trees to be retained on site.
8.1.1
This is the second Monthly EM&A Report presents the
EM&A works during the reporting period from 1 May 2023 to 31 May 2023 in
accordance with the EM&A Manual.
8.1.2
No Action Level or Limit Level exceedance was recorded for 1-hour TSP
monitoring in the reporting period.
8.1.3
No Action Level or Limit Level exceedance was recorded for construction
noise monitoring in the reporting period.
8.1.4
Environmental site inspections were conducted on 5, 12, 17 and 25 May
2023 by the ET in the reporting period.
8.1.5
No environmental complaint was received in the reporting period.
8.1.6
No notification of summons and prosecution was received in the reporting
period.
8.1.7
The ET will keep track on the construction works to confirm compliance
of environmental requirements and the proper implementation of all necessary
mitigation measures.
8.1.8
No change to the EM&A programme was made in this reporting period.
8.2.1
The proposed mitigation measures were properly implemented and were
considered effective and efficient in pollution control.
8.2.2
The ET had no recommendation following the completion of EM&A in the
reporting period.